Implementation of infrastructure for the Integrated Waste Management System in the Region of Western Macedonia

Sector: 
Contracting Authority: 
Date of approval by the IM PPP Committee: 
02.08.2007
Budget: 
49 000 000 €
Funding: 
Project Duration: 
27 years
Final Contractor: 
AKTOR CONCESSIONS - HELECTOR
Date of EIA approval: 
01.12.2014
Date of Contract: 
10.06.2015
Project Development Budget: 
49 000 000 €
Equity: 
18 000 000 €
Lending: 
31 000 000 €
Project type: 
Availability Payments
Type tendering process: 
Closed Procedure
Date Tender: 
05.01.2011
Construction Period: 
2
Operating time: 
25
Project Description: 

The scope of the project is the design, financing, construction, maintenance, technical management and operation of the project in Western Macedonia for up to 27 years.The infrastructure that will be implemented will manage around 120 thousand tonnes of waste per year. The project was named the Year 2013 Agreement on Waste under the award program "Funding Year Award" by World Finance magazine and after a three month evaluation.

Prefecture: 
Current Status: 
It is in operation